Friday, 26 October 2012

Walls Going Up

On Wednesday 17th October the block workers started. There will be nearly 650 150mm blocks that will be laid on top of the concrete strip foundation. We had to wait for the concrete in the foundation to cure properly before we could start the block laying.






The 150mm blocks are laid in a solid pattern then we will start with the 100mm blocks. These will be laid with a 50mm gap between them. There will be approx 6500 100mm blocks used in building the house.


 The block layers laid two rows of blocks and went away so we could infill the house with aggregate and lay a concrete slab. The aggregate was compact in 200mm layers.



 After the aggretgate has reached a predetermined level a 50mm layer of sand was laid and this was also compacted, the sand was used to protect the Radon barrier from damage. The Radon barrier also acts as a damp proof membrane. The Radon barrier has to be taped down at all the open edges.




The Radon barrier.
 A steel mesh was laid on top of the base and this was then ready for concrete. We used 15m3 of concrete which was laid using the hired Telehoist.



The concrete slab took a little longer to lay then we planned!!!

On Thursday 25th October the block layers are back to start laying the 100mm blocks, the lintels and sills also arrived today. The roof trusses are also ordered they will arrive by 2nd November.


Block layers loading blocks on to the slab.


The Telehoist is a also a fork lift truck.!!